fbpx
Homepage» Landowners» How long does it take to develop and construct a solar farm?

How long does it take to develop and construct a solar farm?

Generally, for a 2-5 MW solar farm, the development takes 8-14 months. However, the development timeline largely depends on the utility company’s interconnection process and, local/municipal permitting and approval processes. Construction can take an additional 5-10 months depending on construction timing based on seasonal considerations.